Hi' Ansar,
I hope you can help me further with a question related to this thread I know the thread is old, but i hope you can still help.
From 1 sales order line item I have managed to create WBS-elements i 3 levels. Each WBS-element at level 3 has activities from the same network.
I can create a new sales order line item and thereby add new WBS and network in the same project. (WBS level 1 is the same - just one root)
So far so good!
But I have a problem with the posting
When I make postings at the activities allocated to WBS-elements at level 2 and have settled for the period - the SD-informations are present at the postings (e.g. Sales Type).
But when I make postings at activities at WBS-element level 3 and have settled for the period, I do not have the SD-informations at thi postings.
I do not understand why. Can you help me?
Best regards
Lone Würtz